Stay informed with the latest progress, milestones, and photos from our ongoing bond-funded construction projects.

July 2026: PPS Construction Progress Update

From the day ground was broken, we knew completing a project of this scale in time for the new academic year would be a tight squeeze. It remains an all-hands-on-deck effort, but thanks to the relentless dedication of our construction crews and school operations teams working in overdrive, we determined to make it happen. The building is taking shape, and we cannot wait to open the doors to our students and staff!

Here is where things stand as of mid-July:

  • Major Systems Live: A major milestone was reached this month—we officially powered on the main lighting grid and fired up the boilers for the first time.
  • Interior Finishes: Suspended ceiling grid installations are underway as electrical, HVAC, and telecommunications wiring are capped off and certified. Durable commercial flooring and custom cabinetry/millwork are being fitted across classrooms and common areas.
  • Site & Exterior Prep: Grading and base-layer preparation for the parking lot are nearly complete, clearing the way for final asphalt paving in early August.
  • Original Building Renovations: Professional asbestos abatement continues safely on schedule within the existing facility, paving the way for immediate tie-ins between the original structure and the new wing, and safe demolition of the oldest wing.

The Countdown: What Lies Ahead

Being a little over a month out from opening day means shifting from heavy structural labor to detailed commissioning and readiness. Over the next several weeks, our teams will be executing comprehensive testing of fire alarm systems, emergency egress lighting, security access controls, and air balancing across all HVAC units. Our technology department will begin installing smartboards and AV equipment, and furniture will start to be moved in while a full site scrub-down and detailed room-by-room walkthroughs take place to touch up paint, adjust hardware, and fix minor imperfections.

New classroom almost finished.
Worker installing window

JULY 2026: Groundbreaking at Union Memorial School

We turned the first page on an exciting new chapter for Union Memorial School! On Tuesday, July 7, the Colchester community gathered on the UMS field to officially break ground on our brand-new school addition.

This video captures highlights from our celebration, featuring inspiring remarks from Superintendent Amy Minor, School Board Chair Lindsey Cox, and UMS Principal Colleen Birner. Watch as our wonderful community mingles, future generations of students grab shovels to move the ceremonial pile of dirt, and everyone’s favorite friendly lake monster, Champ, makes a special appearance!

Thank you to everyone who joined us and to the entire community for making this facilities project possible. We can't wait to watch this new space grow!

JUNE 2026: Summer Construction Updates

Construction is about to begin at Union Memorial School. We are thrilled to partner once again with PC Construction as our general contractor. They are the same company currently working at Porters Point School, and they have been wonderful partners throughout this process.

Phase 1: The New Addition

The first phase of the UMS project will focus entirely on constructing the new addition. Crews have arrived this week to set up construction fencing and deliver equipment. We are planning a groundbreaking ceremony for early July and can’t wait to share this milestone with our community.

Summer Playground and Safety

  • Playground Status: We are pleased to announce that the UMS playground will remain open to the community this summer.
  • Changes: The swings and the basketball court will be removed due to their proximity to the construction, but the primary playground structure will remain accessible.
  • Safety First: If you visit UMS this summer, please stay alert to construction vehicles moving through the parking lot and near the fenced areas.

What to Expect This Fall

If your student is attending UMS in the fall, you will receive more detailed construction updates later this summer. For now, please know that the inside of the existing school building will remain exactly the same for the upcoming 2026-27 school year. No construction will take place inside the current building.

The Next Phase at PPS

The time has come to say goodbye to the original wing of Porters Point School. Soon, construction crews will begin work inside the old wing to prepare the different sections for renovation and demolition. Our faculty and staff have done an amazing job packing up the old portion of the school so it’s ready to be moved into the brand-new addition at the end of the summer!

Playground Closure and Gym Construction

Next week, crews will start construction of the new gymnasium at the back of the existing building. Because of the heavy equipment and space required for the gym project, the PPS playground will be closed for the summer. A safety fence and signs will be installed. The good news is that the playground is scheduled to reopen just in time for the start of school in the fall.

Contacting the PPS Front Office

Due to work starting on the original school building, staff will only be on-site intermittently this summer. If you need to speak with Principal Millham or Michelle in the front office, the best way to get in touch is via phone or email.

UMS(1)
UMS
dji_fly_20260615_112128_0145_1781538185532_photo

MAY 2026: Construction Project Update

Construction progress continues over at Porters Point School! Different trade contractors are working on electrical and mechanical systems; sheetrock is going up in the basement and on the first floor; and the interior framing is wrapping up on the second floor. On the outside, we’re starting to see what the final look will be; windows are being installed, and the siding is going up.

CSD PPS Project Wrap-up 5-08-2026 Report

April 2026: Construction Project Update

Construction continues at Porters Point Schools and it's really started to take shape inside and out. Utilities are being installed, and framers are working on walls, windows, and door frames. We plan to do a video tour of the site soon to give a better sense of what's happening inside. The relationships that have formed between the students and construction workers continues to surprise and inspire us!
Unfinished two-story school building on a construction site.

March 2026: Raising The Final Beam

Signed, sealed, and delivered! Check out the moment PPS students and staff gathered to sign the final beam before watching it rise into its permanent home. This addition is now officially being built on the dreams and signatures of the people who make PPS special.

Thanks to our friends at PC Construction for making this moment so special!

February 2026: Construction Progress Update

While the structural progress happening over at Porters Point School is impressive, our partners at PC Construction agree that one of the best parts of the project is when our curious young learners get to engage in a weekly Q&A session with the construction team!
Check out the full blog post from PC Construction to see the progress and learn more about what’s coming for our community!

 

Concrete foundation of school building project
Visit the PC Construction Blog

December 2025: Construction Progress Update

It’s been a busy few months since we broke ground on the Porters Point School addition. What was once an outdated and inaccessible playground is now an active construction site that’s looking more and more like a real building each day.

The construction teams are finishing up their work of stockpiling and removing sand, while the concrete contractor continues the important job of setting wall forms and pouring concrete for the foundation walls. Our teachers and staff, especially those with spaces right next to the work zone, have been amazing. They’ve been able to accept the intermittent noise disruptions and even leaned in at times by taking advantage of their front row seat. Speaking of, the fence line has also become a very popular spot at recess, with students often lining up to watch the crews in action.

District and school personnel meet weekly with the contractors and architects to keep a close eye on everything through detailed updates and progress reports. We’re happy to report that the project is on time and, as planned, crews will continue working straight through the winter months.

 

Three students smiling next to a fence looking at construction.
Wide shot of the construction site with snow

October 2025: Groundbreaking Ceremony at PPS

A significant step toward fulfilling a shared vision for the future of learning was taken this week at the official groundbreaking ceremony at Porters Point School. The event commenced with remarks from the Superintendent, School Board, and Principal, acknowledging the decade-long community effort behind the project. A highlight of the morning was the participation of students, who shared their excitement and dreams for the improved learning spaces. The ceremony concluded with all participants taking part in the ceremonial shoveling of dirt, marking the tangible beginning of this initiative. This successful milestone is a testament to the community's commitment to providing safe, modern, accessible, and inspiring learning environments for all students.

 

October 2025: Construction Begins at PPS

The Porters Point School construction project is set to officially begin! This project marks the start of major improvements and upgrades to the school environment. The district is pleased to be partnering with PC Construction as the general contractor and PCI Consulting as the owner's project manager to oversee the construction of a new addition to the school. The focus of this initial phase is strictly on the exterior addition, meaning classes, routines, and programs inside the existing building will continue as usual throughout the 2025-26 school year.

Site preparation for the new addition is already underway, with temporary fencing being installed and the site prepped over the last few weeks. With the official groundbreaking ceremony happening the week of October 20, area residents will see construction equipment arriving and initial work beginning. While the project is contained to a fenced-off area and the safety of students, staff, and families remains the top priority, there will be impacts to school routines. For instance, the main lane into the school will be shared by school traffic and construction vehicles and although all of the work will take place outside of the existing school, we want to acknowledge that construction noise will occasionally be noticeable during the school day. We are working closely with PC Construction to minimize disruptions wherever possible, but some noise and activity are unavoidable in a project of this size.

The district is committed to keeping the community informed as the project progresses. This new addition represents a significant investment in our students' learning environment and the long-term future of our schools. Regular updates will continue to be shared through the csdbond.org website and direct school communications through ParentSquare.

 

 

Excavator parked next to a construction site with a pile of dirt at the school.

July 2025: New Playground at PPS

The existing playground at Porters Point School (PPS) was located on the site of the planned two-story addition and needed to be relocated before the new school year began. In addition to being the oldest playground in the district, the equipment was more suitable for older students and too challenging for the K–2 age group.

Earlier this spring, PPS Principal Carolyn Millham shared at a Colchester School Board meeting how input was gathered from both students and staff to help shape the design of the new playground. A central theme that emerged was accessibility, ensuring the new space would be inclusive and usable for students of all abilities.

The new K-2 playground was installed behind the school in late July and is now ready for students and neighborhood youth to enjoy! The old playground is scheduled for mid-August and will be completed before school starts.

Once our preschool program is relocated at the end of the K-2 construction phases, a second section of the playground will be added that will feature preschool-friendly equipment.

 

Newly installed playground at PPS.
DJI_20240814143108_0048_D.MP4.00_00_17_45.Still001

June 2025: General Contractor Selection Process for PPS Project

 

Several companies expressed interest in serving as the general contractor for the first bond-funded construction project at Porters Point School. At a June meeting, Chief Financial and Operations Officer George Trieb reported that the district conducted extensive reference checks and found all applicants to be large, reputable firms that are financially sound and fully capable of completing the project.

Each company met the district’s pre-qualification criteria and was invited to submit detailed bids. The School Board is expected to review those bids in early September, with groundbreaking anticipated in November.

 

Time_Icon_White

Construction Timeline

A snapshot of where we've been and where we're going. Explore key milestones and upcoming construction activities.

2019-01-01

November 2024

Colchester voters approve a $115 millon school improvement bond.

2019-01-01

2020-01-01

Winter 2024 - Spring 2025

Architects and employees at Porters Point School work to finalize floor plans and building layout decisions.

2020-01-01

2021-01-01

July/August 2025

New playground installed at PPS in preparation for building the addition on the site of the former structure.

2021-01-01

2019-01-01

September 2025

Bids for the general contractor of the PPS project are received and reviewed by the Colchester School Board with the goal of final selection by the end of September.

2019-01-01

2019-01-01

November 2025

Phase 1 of the PPS project is anticipated to begin in November with the groundbreaking of a new two-story addition. Construction on the new addition is expected to continue through the summer of 2026.

2019-01-01

2019-01-01

Summer 2026

Phase 2 of construction at PPS begins with the demolition of the school’s oldest wing and renovation of the remaining wing. Once demolition is complete, parking lot design and paving will begin. This phase is expected to continue through the winter and spring of 2027.

2019-01-01

2019-01-01

August 2026

The first phase of construction at the UMS Project takes place with the groundbreaking of the new two-story addition. The UMS project will follow a similar timeline to the PPS project. 

2019-01-01

2019-01-01

August 2027

The PPS Project is expected to be fully completed by the start of the 2027-28 school year. 

2019-01-01

2019-01-01

Beyond 2026-27

As we get closer to starting on the UMS and CMS projects, we will add more detailed milestones to the timeline.

2019-01-01

FOLLOW US ON SOCIAL

Stay connected with our district on social media for real-time updates on bond renovations and improvements! You'll get behind-the-scenes looks at construction progress, timelines, and how these upgrades will directly benefit students and the community. It's the easiest way to stay informed, celebrate milestones, and see your investment in action.