Here are some answers to questions we've received about the bond. If you have additional questions, please submit them using the form on this page.
Tuesday, November 5, 2024
A school bond is a type of long-term financing used by public school districts to fund brick-and-mortar projects. School boards place these measures on the ballot to be considered by the voting public. Without this measure, the district would not have the funds to significantly address delayed maintenance, insufficient space, and safety concerns because the annual operating budget cannot cover it all.
Existing classrooms at PPS and UMS will be renovated, the oldest wings will be demolished and a new two story addition will create dedicated spaces for a cafeteria, physical education, and the preschool program. All of the mechanical and infrastructure will be replaced or updated.
The former preschool classrooms at MBS will be renovated into spaces to provide services for students.
At CMS, the building will see an overhaul of the layout, including classroom spaces and multi-purpose spaces like the cafeteria and gymnasium. The U-shaped building design will be connected to create a square, making the existing courtyard internal and creating a better flow around the building. The main entry will be relocated to the front of the building. Additional classrooms will be added to support several subjects currently being taught from a mobile cart.
At CHS, the roof will be replaced, and we will address the boilers and windows if possible.
Over the last decade, members of the school board have been grappling with what to do with the district’s aging facilities. The plan was in motion to put a bond on the November 2020 ballot, but the pandemic's impact on the community stalled that schedule. Just four years later and the same projects have increased in cost. Architects and engineers are reporting that the longer the community waits, the higher the cost will be. They also noted that supply chains have improved considerably, and contractors are becoming more available, making it an ideal time to take on the project.
The average home in Colchester is assessed at $350,000. Using that home as an example, their estimated contribution to the loan repayment will be:
- 2027: $43 for the year (about $4 per month)
- 2028: $121 for the year (about $10 per month)
- 2029: $330 for the year (about $28 per month)
- 2030: $534 for the year (about $45 per month)
- 2031: $733 for the year (about $61 per month)
- 2032: Starting this year, the bond payment will decrease slightly each year as the principal loan balance is paid down.
Approximately 61% of Colchester homeowners qualify for Vermont’s Property Tax Credit and would contribute to loan repayment on a sliding scale based on income.
There are more details about the structure of the bond and repayment on the Bond Details & Impact page of the website.
A professional cost estimator, experienced with local materials and labor, was hired to create detailed budgets for each building in the project. Their estimates were based on drawings and specifications prepared by the architectural and engineering design team.
The information included scale plans and elevations, detailed information on structural, mechanical, electrical, and fire safety systems, and identification of exterior and interior building materials. Each building also received a comprehensive accounting of site costs for paving, sidewalks, playgrounds, stormwater treatment, and wastewater disposal.
Each estimate included over ten pages of line item costs, resulting in a much more accurate estimate than a simple square-foot methodology would produce.
In addition, the budget provides for several contingencies and other anticipated project costs.
- The estimate includes provisions for temporary construction to provide interim spaces during the projects' intermediate construction phases. These costs are significantly less than the cost of large numbers of temporary classrooms, which would significantly reduce the available space for parking, playgrounds, and general traffic flow.
- An annual inflation factor was added to each project to allow construction on each building to happen consecutively and not overburden the capacity of the available workforce by trying to complete them all at once. A local general contractor with an extensive public school resume was consulted and confirmed the cost estimates and construction timeline for each building.
- A typical design/bid/construction contingency has been included to allow for changes in the market prior to bidding and changes in the scope of work after bidding.
- Other “soft costs” such as permitting fees, architectural and engineering services, owner’s rep, testing services, moving and storage expenses, and insurance have also been factored into the overall project budget.
In the end, these costs resulted in per-square-foot projections that were very much in line with those of other recently bid projects.
In 2007, the State of Vermont placed a moratorium on school construction aid. While there has been some recent talk about resurrecting it, no real progress has materialized. It is unlikely that school construction aid will return for Vermont schools and taxpayers. However, if it does become available, Colchester will apply for those funds or assistance to offset the cost to taxpayers.
The short answer is no; the law doesn’t allow it. The Vermont State Legislature has created organizations, boards, and funding that separate local municipal government services and education. State statute restricts using Local Option Tax funds toward school expenses. (For reference, the State Statutes are 16 V.S.A. Section 4029 and 24 V.S.A. Section 138.)
The construction project will be completed in three phases, starting in November of 2025 and ending in 2030, allowing bond payments to increase incrementally. The timeline has construction beginning with PPS, then UMS, followed by CMS and MBS, and concluding with CHS.
The benefit of this proposal is that it allows the district to occupy 100% of the existing school while the new areas are being constructed. Naturally, there will be some day-to-day distractions with equipment and crews on the campus, but the school schedule and locations will be operational during renovations. The construction timeline has been established to make maximum use of the summer breaks and when students are not in session.
Most of our schools have little to no investments for upgrades since they were built about 60 years ago. At this point, some sections are beyond what is fiscally responsible to repair. Many key components in these buildings are at the end of their useful life. Infrastructure such as insulation, plumbing, HVAC, and electrical need significant attention.
The state’s timeline for PCB testing has experienced some delays, which has impacted when schools across Vermont, including ours, are tested. We’re pleased to share that Malletts Bay School (MBS) was tested in April 2024, with results in June showing no action is required. Colchester Middle School (CMS), originally scheduled for testing in 2023, is still awaiting its turn. The remaining schools are set for testing in the summer or fall of 2025, but that may be pushed out since the state extended the overall testing deadline to the end of 2027.
The state’s PCB testing schedule played a role in planning our renovation timeline, and we’ve been thoughtful in our approach. For example, the sections of the K-2 schools that are older and more likely to require attention will be removed entirely during the renovation process. Meanwhile, the newer portions of those buildings that are much less likely to have any PCB issues will be renovated. For CMS, we expect the state to complete testing before renovations begin, ensuring that we can proceed with the best information available.
We will not start any renovation until we have received the PCB testing results. Regardless of whether the bond passes, if PCBs are found at levels requiring action, the district would need to follow all necessary guidelines for remediation response. If we are preparing for construction, we’d be able to adjust the plans to include expert-recommended solutions for affected areas.
Building a new Pre-K to Grade 2 school and closing Porters Point and Union Memorial was extensively considered during the planning process.
The logical and most cost-effective location to build a new school would be on land the district already owns. The only space large enough for a facility to hold over 500 students would be on the high school campus in the wooded area on the corner of Blakely Road and Laker Lane. The district contracted a traffic study that concluded there would be a tremendous increase during peak hours on the already congested Blakely roadway.
Through our community engagement sessions last winter, we heard overwhelmingly that residents deeply valued and preferred keeping the two neighborhood schools.
The plan includes demolishing the oldest wings at both schools and constructing a new two-story addition while keeping and renovating an exsisting newer wing.
Supporting a bond initiative benefits the entire community through property values and attracting new families.
Young people are our future workforce, homeowners, and taxpayers. Their education and the support they receive in school prepare them for the next step into adulthood, and the stronger their foundation, the better their outcomes.
Investing in better facilities ensures safer, healthier environments for everyone. Even without children in the schools, supporting education reflects a commitment to the community’s long-term success and well-being.